With two main areas of construction still under progress at Bellarmine, students were informed of the Owsley B. Frazier stadium and Sienna Hall’s advancement. There will now be monthly updates to students to keep them informed on the construction.
Currently, the stadium development is slow because of all the October rain. The field is also the lowest spot on campus and therefore has a lot of standing water that will not dry up in these cold months. So far, the footers and piers are being poured for the bleachers, foundations and pole stubs are in place for the stadium lights, and the rock base has been started for the track. Also, there has been progress on the hillside by Our Lady of the Woods Chapel and the curbing along Newburg Road has started and the sidewalk will following shortly. The completion of the stadium is being looked on with the hopeful eyes of the lacrosse team, who have scheduled the second half of their season at home in order to play on their new home field. Whether or not the stadium, which broke ground last April, will be done yet or not is another story.
Rain was not such an obstacle for the construction of Sienna because it is on a hillside. It has remained on schedule and so far, footers and foundation are complete in about 60% of the building. Foundations and walls are currently being constructed in the gatehouse section and progress is moving according to schedule. The eastern most section of the residence hall has the first floor walls in place and decking is scheduled for this week. The parking lot for this hall is curbed and base coat of asphalt is in place. Hopefully the dorm will be ready to go by the beginning of next school year.
Sincerely,
Jessica Neiser
Currently, the stadium development is slow because of all the October rain. The field is also the lowest spot on campus and therefore has a lot of standing water that will not dry up in these cold months. So far, the footers and piers are being poured for the bleachers, foundations and pole stubs are in place for the stadium lights, and the rock base has been started for the track. Also, there has been progress on the hillside by Our Lady of the Woods Chapel and the curbing along Newburg Road has started and the sidewalk will following shortly. The completion of the stadium is being looked on with the hopeful eyes of the lacrosse team, who have scheduled the second half of their season at home in order to play on their new home field. Whether or not the stadium, which broke ground last April, will be done yet or not is another story.
Rain was not such an obstacle for the construction of Sienna because it is on a hillside. It has remained on schedule and so far, footers and foundation are complete in about 60% of the building. Foundations and walls are currently being constructed in the gatehouse section and progress is moving according to schedule. The eastern most section of the residence hall has the first floor walls in place and decking is scheduled for this week. The parking lot for this hall is curbed and base coat of asphalt is in place. Hopefully the dorm will be ready to go by the beginning of next school year.
Sincerely,
Jessica Neiser
